| SMITHSONIAN INSTITUTION - ENERGY MANAGEMENT BRANCH - 202-633-0119 | |||||
| QUARTERLY BUILDING SUMMARIES - VICTOR BUILDING | |||||
| FY 2002 | |||||
| VICTOR BUILDING | GSF: | 477,077 | |||
| YEAR-TO-DATE | |||||
| USAGE | COST | KBTUs | KBTUs / GSF | $$ / GSF | |
| Electricity (KWH) | 8,323,250.0 | $ 503,107.68 | 28,400,593.65 | 59.53 | $ 1.05 |
| Water (Mgallons) | 5,779.0 | $ 25,875.13 | |||
| TOTALS | $ 528,982.81 | 28,400,593.65 | |||
| QUARTER 1 | |||||
| USAGE | COST | KBTUs | KBTUs / GSF | $$ / GSF | |
| Electricity (KWH) | 2,206,982.0 | $ 131,755.96 | 7,530,663.98 | 15.79 | $ 0.28 |
| Water (Mgallons) | 1,368.0 | $ 6,273.65 | |||
| TOTALS | $ 138,029.61 | 7,530,663.98 | |||
| QUARTER 2 | |||||
| USAGE | COST | KBTUs | KBTUs / GSF | $$ / GSF | |
| Electricity (KWH) | 1,979,328.0 | $ 122,297.41 | 6,753,863.00 | 14.16 | $ 0.26 |
| Water (Mgallons) | 1,616.0 | $ 6,783.61 | |||
| TOTALS | $ 129,081.02 | 6,753,863.00 | |||
| QUARTER 3 | |||||
| USAGE | COST | KBTUs | KBTUs / GSF | $$ / GSF | |
| Electricity (KWH) | 2,023,722.0 | $ 135,571.79 | 6,905,344.21 | 14.47 | $ 0.28 |
| Water (Mgallons) | - | $ - | |||
| TOTALS | $ 135,571.79 | 6,905,344.21 | |||
| QUARTER 4 | |||||
| USAGE | COST | KBTUs | KBTUs / GSF | $$ / GSF | |
| Electricity (KWH) | 2,113,218.0 | $ 113,482.52 | 7,210,722.46 | 15.11 | $ 0.24 |
| Water (Mgallons) | 2,795.0 | $ 12,817.87 | |||
| TOTALS | $ 126,300.39 | 7,210,722.46 | |||
| FY 2001 | |||||
| VICTOR BUILDING | GSF: | ||||
| YEAR-TO-DATE | |||||
| USAGE | COST | KBTUs | KBTUs / GSF | $$ / GSF | |
| Electricity (KWH) | 7,597,400.0 | $ 542,851.73 | 25,923,848.28 | 54.34 | $ 1.14 |
| Water (Mgallons) | 4,850.2 | $ 21,664.45 | |||
| TOTALS | $ 564,516.18 | 25,923,848.28 | |||
| QUARTER 1 | |||||
| USAGE | COST | KBTUs | KBTUs / GSF | $$ / GSF | |
| Electricity (KWH) | 1,359,832.0 | $ 93,298.66 | 4,640,018.75 | 9.73 | $ 0.20 |
| Water (Mgallons) | 1,484.2 | $ 6,947.67 | |||
| TOTALS | $ 100,246.33 | 4,640,018.75 | |||
| QUARTER 2 | |||||
| USAGE | COST | KBTUs | KBTUs / GSF | $$ / GSF | |
| Electricity (KWH) | 1,827,152.0 | $ 115,204.75 | 6,234,608.05 | 13.07 | $ 0.24 |
| Water (Mgallons) | 1,247.0 | $ 5,344.64 | |||
| TOTALS | $ 120,549.39 | 6,234,608.05 | |||
| QUARTER 3 | |||||
| USAGE | COST | KBTUs | KBTUs / GSF | $$ / GSF | |
| Electricity (KWH) | 2,159,603.0 | $ 144,823.69 | 7,368,997.36 | 15.45 | $ 0.30 |
| Water (Mgallons) | 1,232.0 | $ 5,371.92 | |||
| TOTALS | $ 150,195.61 | 7,368,997.36 | |||
| QUARTER 4 | |||||
| USAGE | COST | KBTUs | KBTUs / GSF | $$ / GSF | |
| Electricity (KWH) | 2,250,813.0 | $ 189,524.63 | 7,680,224.12 | 16.10 | $ 0.40 |
| Water (Mgallons) | 887.0 | $ 4,000.22 | |||
| TOTALS | $ 193,524.85 | 7,680,224.12 | |||